Piermont Grand Sumang Walk Indicative Status of TOP*: Obtained in January 2023
LeaseholdExecutive Condominium
99-year leasehold from 4 June 2018
1 |
Foundation Work |
Completed |
2 |
Reinforced Concrete Framework |
Completed |
3 |
Brick Walls |
Completed |
4 |
Ceilings |
Completed |
5 |
Door and Window Frames |
Completed |
6 |
Car Parks, Roads and Drains |
Completed |
7 |
TOP |
Obtained |
Boulevard 88 Orchard Boulevard Indicative Status of TOP*: March/April 2023
FreeholdMixed Development
1 |
Foundation Work |
Completed |
2 |
Reinforced Concrete Framework |
Completed |
3 |
Brick Walls |
Completed |
4 |
Ceilings |
Completed |
5 |
Door and Window Frames |
Completed |
6 |
Car Parks, Roads and Drains |
Completed |
7 |
TOP |
Nil |
Haus on Handy Handy Road Indicative Status of TOP*: March/April 2023
LeaseholdCondominium
99-year leasehold from 7 May 2018
1 |
Foundation Work |
Completed |
2 |
Reinforced Concrete Framework |
Completed |
3 |
Brick Walls |
Completed |
4 |
Ceilings |
Completed |
5 |
Door and Window Frames |
Completed |
6 |
Car Parks, Roads and Drains |
Completed |
7 |
TOP |
Nil |
Amber Park Amber Gardens Indicative Status of TOP*: Q4 2023
FreeholdCondominium
1 |
Foundation Work |
Completed |
2 |
Reinforced Concrete Framework |
In Progress |
3 |
Brick Walls |
In Progress |
4 |
Ceilings |
In Progress |
5 |
Door and Window Frames |
In Progress |
6 |
Car Parks, Roads and Drains |
Nil |
7 |
TOP |
Nil |
Sengkang Grand Residences Compassvale Bow Indicative Status of TOP*: Q3 2023
LeaseholdIntegrated Development
99-year leasehold from 13 November 2018
1 |
Foundation Work |
Completed |
2 |
Reinforced Concrete Framework |
In Progress |
3 |
Brick Walls |
In Progress |
4 |
Ceilings |
In Progress |
5 |
Door and Window Frames |
In Progress |
6 |
Car Parks, Roads and Drains |
Nil |
7 |
TOP |
Nil |
Irwell Hill Residences Irwell Hill (off Irwell Bank Road) Indicative Status of TOP*: Q1 2025
LeaseholdCondominium
99-year leasehold from 13 April 2020
1 |
Foundation Work |
Completed |
2 |
Reinforced Concrete Framework |
In Progress |
3 |
Brick Walls |
In Progress |
4 |
Ceilings |
In Progress |
5 |
Door and Window Frames |
In Progress |
6 |
Car Parks, Roads and Drains |
Nil |
7 |
TOP |
Nil |
Piccadilly Grand Northumberland Road Indicative Status of TOP*: Q1 2025
LeaseholdIntegrated Development
99 years commencing from 2 August 2021
1 |
Foundation Work |
In Progress |
2 |
Reinforced Concrete Framework |
Nil |
3 |
Brick Walls |
Nil |
4 |
Ceilings |
Nil |
5 |
Door and Window Frames |
Nil |
6 |
Car Parks, Roads and Drains |
Nil |
7 |
TOP |
Nil |
CanningHill Piers Clarke Quay Indicative Status of TOP*: Q2 2027
LeaseholdIntegrated Development
99 years leasehold from 17 September 2021
1 |
Foundation Work |
Nil |
2 |
Reinforced Concrete Framework |
Nil |
3 |
Brick Walls |
Nil |
4 |
Ceilings |
Nil |
5 |
Door and Window Frames |
Nil |
6 |
Car Parks, Roads and Drains |
Nil |
7 |
TOP |
Nil |
Copen Grand Tengah Garden Walk Indicative Status of TOP*: Q4 2027
LeaseholdExecutive Condominium
99 years commencing from 31 August 2021
1 |
Foundation Work |
In Progress |
2 |
Reinforced Concrete Framework |
Nil |
3 |
Brick Walls |
Nil |
4 |
Ceilings |
Nil |
5 |
Door and Window Frames |
Nil |
6 |
Car Parks, Roads and Drains |
Nil |
7 |
TOP |
Nil |
*Estimated date subject to changes. Updated as at 30 March 2023. This page will be updated quarterly.