Piermont Grand Sumang Walk Indicative Status of TOP*: Obtained in January 2023

LeaseholdExecutive Condominium

99-year leasehold from 4 June 2018

1 Foundation Work Completed
2 Reinforced Concrete Framework Completed
3 Brick Walls Completed
4 Ceilings Completed
5 Door and Window Frames Completed
6 Car Parks, Roads and Drains Completed
7 TOP Obtained

Boulevard 88 Orchard Boulevard Indicative Status of TOP*: March/April 2023

FreeholdMixed Development

Freehold

1 Foundation Work Completed
2 Reinforced Concrete Framework Completed
3 Brick Walls Completed
4 Ceilings Completed
5 Door and Window Frames Completed
6 Car Parks, Roads and Drains Completed
7 TOP Nil

Haus on Handy Handy Road Indicative Status of TOP*: March/April 2023

LeaseholdCondominium

99-year leasehold from 7 May 2018

1 Foundation Work Completed
2 Reinforced Concrete Framework Completed
3 Brick Walls Completed
4 Ceilings Completed
5 Door and Window Frames Completed
6 Car Parks, Roads and Drains Completed
7 TOP Nil

Amber Park Amber Gardens Indicative Status of TOP*: Q4 2023

FreeholdCondominium

1 Foundation Work Completed
2 Reinforced Concrete Framework In Progress
3 Brick Walls In Progress
4 Ceilings In Progress
5 Door and Window Frames In Progress
6 Car Parks, Roads and Drains Nil
7 TOP Nil

Sengkang Grand Residences Compassvale Bow Indicative Status of TOP*: Q3 2023

LeaseholdIntegrated Development

99-year leasehold from 13 November 2018

1 Foundation Work Completed
2 Reinforced Concrete Framework In Progress
3 Brick Walls In Progress
4 Ceilings In Progress
5 Door and Window Frames In Progress
6 Car Parks, Roads and Drains Nil
7 TOP Nil

Irwell Hill Residences Irwell Hill (off Irwell Bank Road) Indicative Status of TOP*: Q1 2025

LeaseholdCondominium

99-year leasehold from 13 April 2020

1 Foundation Work Completed
2 Reinforced Concrete Framework In Progress
3 Brick Walls In Progress
4 Ceilings In Progress
5 Door and Window Frames In Progress
6 Car Parks, Roads and Drains Nil
7 TOP Nil

Piccadilly Grand Northumberland Road Indicative Status of TOP*: Q1 2025

LeaseholdIntegrated Development

99 years commencing from 2 August 2021

1 Foundation Work In Progress
2 Reinforced Concrete Framework Nil
3 Brick Walls Nil
4 Ceilings Nil
5 Door and Window Frames Nil
6 Car Parks, Roads and Drains Nil
7 TOP Nil

CanningHill Piers Clarke Quay Indicative Status of TOP*: Q2 2027

LeaseholdIntegrated Development

99 years leasehold from 17 September 2021

1 Foundation Work Nil
2 Reinforced Concrete Framework Nil
3 Brick Walls Nil
4 Ceilings Nil
5 Door and Window Frames Nil
6 Car Parks, Roads and Drains Nil
7 TOP Nil

Copen Grand Tengah Garden Walk Indicative Status of TOP*: Q4 2027

LeaseholdExecutive Condominium

99 years commencing from 31 August 2021

1 Foundation Work In Progress
2 Reinforced Concrete Framework Nil
3 Brick Walls Nil
4 Ceilings Nil
5 Door and Window Frames Nil
6 Car Parks, Roads and Drains Nil
7 TOP Nil

For more updates about your new CDL home and TOP FAQs, please visit  Homebuyer ePortal

*Estimated date subject to changes. Updated as at 30 March 2023. This page will be updated quarterly.